I get emailed the previous day's work period report

I set it up to email the work period report. The first day I get the correct report. The next day I get the previous day’s report. Then the next day I get the correct report. I’m not sure where to look to figure this out.

You got the delay in there to allow report to save before emailing?

No delay. I will try that. Thank you

I think there was a newer method that handled it but havnt looked for a whilr, origionally you saved then emailed but needed to delay sending as file wouldnt be ready quick enough for email straight away.